35 Young Crescent Drury

This project is located near the rural area of Drury. The preliminary civil work includes various complex tasks, such as upgrading two water mains under different main roads, upgrading the wastewater pump station located about a 5-minute drive from the site, upgrading the public footpath at the site entrance, and upgrading the public AT lighting on Young Crescent, among others.
With a comprehensive update of the civil work, we believe this development project of 19 compact units will ultimately provide a comfortable and peaceful experience for the residents living here.

Starting date Apr 2024

Estimated Practical completion date Apr 2025

Contract Value (GST exclusive) 5.8 million

Gross floor area (m2) 1778

Project scale 18 terraces and 1 single house