EdgeWest in Westgate offers a range of 42 beautifully presented family homes with the rare combination of location and lifestyle. For the busy commuter, the convenience of motorway access and public transport options will take the stress out of your work day, while North West Mall provides endless possibilities for shopp;ing and entertainment during evenings and weekends.
Construction: EdgeWest sits on a very flat site. The client expects the total construction period including all civil works and building construction to be completed within 12 months. Another feature of the construction of this project is to build up the acoustic fence at the rear side of the site, to reduce noise from the nearby motorway.
Starting date May-21
Practical completion date Aug 2022
Contract Value (GST exclusive) $9,500,000
Gross floor area (m2) 3,446
Project scale 42 unit terraces